World’s biggest jacked tunnels save time and money
The tunnel jacking for Boston’s Central Artery project – known
as the Big Dig – is by far the largest, most complex project of its
kind in the world. Requiring a quantum leap in scale – well over
ten times the size of any jacked tunnels attempted in the USA
before – it has involved major innovation. Recognised as the most
challenging component of the Central Artery Project – which takes
much of the city’s highway network underground, removing heavy
traffic congestion and pollution – the tunnel jacking has delivered
a low maintenance, robust construction while adding substantial
environmental advantages and contributed to over US$300 million in
construction savings.
Tunnelling under a live railway
Creating Boston’s I-90/I-93 interstate interchange meant
constructing multi-lane highway tunnels under the approach to South
Station. This complex network of seven interconnecting railtracks
carries over 40 000 commuters and 400 train movements per day.
Before our team’s involvement the design concept being developed
required five phased relocations of the railway – an approach
unacceptable to the railway authorities. Apart from moving the
tracks, each phase would have involved re-establishing the
extensive control systems which included sensitive buried fibre
optics. All this would have been very time consuming and a major
safety issue. Our alternative enabled three full-size interstate
highway tunnels – totalling over 240m in length with single
elements weighing up to 30,000t – to be jacked under an operating
railway with no track relocations, train speed restrictions or
interruptions to the service and with an excellent safety
record.
This alternative to traditional cut and cover methods also reduced
excavation considerably, bringing added environmental benefit by
minimising transportation of heavily contaminated materials through
the city. Another major advantage was that the project allowed
overhead electrification to proceed concurrently with tunnel
construction, thus advancing a safer and more efficient railway
service for commuters.
Experts from Mott MacDonald and our North American company Hatch
Mott MacDonald introduced the alternative of tunnel jacking at the
bid stage and won the design contract as a specialist tunnelling
sub-consultant to the local consultants JV, Maguire-Harris. This
was on a cost plus fixed fee basis and the Mott MacDonald
involvement was extended throughout the construction phase
providing value engineering and site supervision services. The
Standard Federal fixed price construction contract for the
intersection was awarded to the JV of Slattery-Skanska, Interbeton,
White and Perini for US$400m, with the tunnel jacking element being
US$140m. Specialist tunnel jacking expertise was provided by
Skanska, Edmund Nuttall and John Ropkins Ltd.
Site constraints
The jacked tunnel site is located at the intersection of the I-90
and I-93 interstate highways. This was the most complex contract in
the entire Central Artery Project with severe spatial and
operational constraints. The space for construction was limited to
an area of just 300m by 700m enclosed between the interstate
highways, the railway system and a waterway. The limitations were
significantly eased by the introduction of tunnel jacking since the
railway no longer needed the phased relocations. However, available
construction space was still considerably less than the normal
needs for tunnel jacking. This was overcome by the unique use of
combined jacking pits and global ground freezing.
Global ground freezing
The ground freezing for the jacked tunnels was the largest ever
undertaken beneath an operating railway. It greatly simplified the
breaching of the headwalls of the jacking pits and created a safer
working environment at the tunnel face. It also allowed the unique
temporary ‘parking’ of a 30,000t box unit beneath the railway which
successfully addressed the spatial constraints of the jacking pits.
In addition, frozen ground presented a safer and easier way to deal
with the numerous obstructions encountered in the tunnel face. The
ground conditions beneath the railway presented the most
challenging array of mixed face conditions including two centuries
of uncontrolled fill and buried obstacles overlying compressible
strata, which became major obstacles during the tunnelling works.
These included old masonry foundations, reinforced concrete, a
buried trackway and forests of timber piles.
With the major benefits, ground freezing brought its own
challenges. Excavation at the tunnel face was safer but this
required development of enhanced performance for the British
Webster roadheaders. Further innovations were introduced to cope
with the large ground movements created by the freezing. These
included a system of hydraulic jacks to allow pressure relief to
the headwalls and a heating control system in the ground and tunnel
walls to avoid the tunnels becoming locked in the ground.
Special anti-drag system
A special new anti-drag system (ADS) was developed which utilised
hundreds of steel ropes above and beneath the tunnel units. Its key
role was to de-couple the jacked tunnel boxes from the ground and
infrastructure above. This prevented the tendency of the ground to
move laterally with the tunnel as it is jacked forward. The ADS –
the highest capacity, most extensive such system ever used – also
provided improved alignment control with additional sets of steel
ropes beneath the tunnels. Trains safely moved uninterrupted
overhead as the tunnel sections were installed below the tracks at
a rate of 1-2m per day.